The meeting open with discussions regarding the construction at the Public Landing. Agregate Paving will be there on Wednesday to start the fine grading. A binder course 2 1/2″ thick and a top of 1″ will start either Thursday or Friday.
The piles for the new building has been added to the current contractor Argus who will subcontract to SeaShore. This should start possibly the end of this week and be done before paving starts.
New curbing will be started end of November after the binder is set. A binder will definitely be down before winter.
The big piles of dirt will be used to fill in some of the loom rather than having the expense of carting the piles away.
New benches and Seagull proof trash cans will be installed in the Spring.
All light bases have been installed except behind the loom pile.
There’s only 1 storm ceptor on the west side near the Winthrop Yacht Club. It has both an oil and water separator.
The new parking lot plans will include 35 – 40 more spots.