Progress is being made with the last of the electrical lines installed and gas company ready to go.
Possibly binder will be down by Bob DeLeo’s event, if not, soon. The finish coat will be started prior to winter season.
Argus has agreed to drive the piles and install grey beams for the new building before paving is done.
All trees were transplanted and Norm Siefert’s trees will be saved.
The new building desing has finally been settled upon and waiting for David Vine to finish the bid documents. Then the plans and specifications will go out to bid from the town. The bidding on the building is from slab, underground, etc.
The silk granite will be reused for the new curbing.
Next meeting: November 2, 2009